Use the following project information.

Activity Activity Time (weeks) Immediate Predecessor(s)

A 3 none
B 4 A
C 2 B
D 5 B
E 4 C
F 3 D
G 2 E,F

Calculate the completion time for the project. Completion time = weeks

Determine which activities are included on the critical path.

A, B, C, E, G
A, B, D, F, G

Purchase this Solution

Solution Summary

This posting contains solution to following project management problem.

Solution Preview

Hi

Please find attached the Excel versionresponse to your question.

Hope you find it useful.

Use the following project ...

Purchase this Solution


Free BrainMass Quizzes
SWOT

This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.

Employee Orientation

Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.

Basic Social Media Concepts

The quiz will test your knowledge on basic social media concepts.

Lean your Process

This quiz will help you understand the basic concepts of Lean.

Change and Resistance within Organizations

This quiz intended to help students understand change and resistance in organizations