    Determining completion time of a project with activities included

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    See the attached file.

    Activity Preceding Activities Normal Time (weeks) Crash Time (weeks) Expediting (Crashing) cost per week ($)
    A - 9 8 3,000
    B A 19 15 1,800
    C A 15 14 2,000
    D B,C 5 5 -
    E C 10 6 4,000
    F D,E 2 1 1,000

    Question 1.
    A restaurant chain is building a new restaurant. The following are activities that need to be completed before the restaurant is opened.

    What is the completion time for the project?
    Project Completion Time = ## weeks

    How many weeks should the project completion time be reduced?
    Project Reduction = ## weeks

    What is the project duration if all activities are crashed to their minimum?
    Project Duration = ## weeks

    Refer to pages 197-201 for guidance - Those are attached.

    Question 2.
    (Refer to the project shown in Figure 5-10 (see page 156). The facility used by activities "c" and "d" is scarce. Given the following priority rules, which activity ("c" or "d") would you assign the facility first?)
    Refer to pages 217-218 for guidance - Attached
    Files attached.

    Given the following priority rules, which activity ("c" or "d") would you assign the facility first?

    Minimum slack first: Activity c - or - d
    Most followers (successors) : Activity c - or - d
    Most critical followers: Activity c - or - d
    Shortest task duration first: Activity c - or - d
    As late as possible: Activity c - or - d.

    © BrainMass Inc. brainmass.com October 10, 2019, 6:51 am ad1c9bdddf
    https://brainmass.com/business/business-management/completion-time-project-activities-included-558969

    Attachments

    Solution Summary

    The solution determines the completion time of a project with activities included.