Explore BrainMass
Share

Landscape Project Management: Critical Path

This content was STOLEN from BrainMass.com - View the original, and get the already-completed solution here!

Given the following project to landscape a new building site.

Activity Immediate Predecessor Activity duration(days) Resources used

A: Get Plants - 2 X,Y
B: Get flowers A 2 X
C: Obtain soil A 3 X
D: Obtain Fertilizer B,C 4 X,Y
E: Select Labor D 3 W,X
F: Set date D 1 W,X,Y
G: BEGIN E,F 2 X,Y

(a) Find the critical path and project duration in days.
(b) Given that each resource is assigned 100% to each task, identify the resource constraints.
(c) Level the resources and determine the new project duration and critical path
(d) Identify what alternative solutions can be used to shorten the project duration and not over-allocate the resources.

© BrainMass Inc. brainmass.com October 25, 2018, 5:56 am ad1c9bdddf
https://brainmass.com/business/project-management/landscape-project-management-critical-path-440705

Solution Summary

The solution does a great job of answering the question. The solution is brief and concise and very easy to follow along. All the steps are clearly shown and Excel formulas are provided so that the student can answer similar questions in the future. It can be easily understood by anyone with a basic understanding of the topic. Overall, an excellent solution.

$2.19
See Also This Related BrainMass Solution

Critical Path Project Management

Poderosa Construction has budgeted $350,000 to build a new clubhouse. They use a mixture of union and nonunion personnel. Grading of the land, electrical, and plumbing work is subcontracted out to union shops. The actual construction of the project, though supervised by union carpenters, is performed mainly by nonunion laborers to conserve costs. Project planning has produced the following chart:

(See attachment)

(a) Use the critical path method (CPM) to calculate the earliest start and finish times for all
activities (forward pass) and the latest start and finish times for all activities (backward pass). (b) Compute the slack time for each activity and identify the critical activities.
(c) Identify all critical path(s). What is the project completion time?
(d) How long can the activity (C): "Hire nonunion labor" be delayed without delaying the
minimum completion time of the whole project?
(e) If activities (D) and (H) are each delayed by 3 days, how long will the whole project be
delayed?
(f) If activity (K) is delayed by 3 days, how long will the whole project be delayed?
(g) If activity (D) is delayed by 1 day (that is the duration of activity (D) changes from 8 days to 9 days and completion times of all other activities remain the same), how many critical paths do we have now in the whole project? What are they?

View Full Posting Details