Project Management: Analysis of Critical Paths

Suppose the length of critical path in a project is 50 days. The probability of completing the project within 50 days is:

Less than 50%

Greater than 50%

Equal to 50%

Can not be determined from the above data

Solution Preview

If the length of the critical path is 50 days, the chances to complete the project in 50 days would be less than 50% because the critical path is the ...

Solution Summary

This solution explains the correct answer to the project management multiple choice question listed.