Project Management: Analysis of Critical Paths
Not what you're looking for?
Suppose the length of critical path in a project is 50 days. The probability of completing the project within 50 days is:
Less than 50%
Greater than 50%
Equal to 50%
Can not be determined from the above data
Purchase this Solution
Solution Summary
This solution explains the correct answer to the project management multiple choice question listed.
Solution Preview
If the length of the critical path is 50 days, the chances to complete the project in 50 days would be less than 50% because the critical path is the ...
Purchase this Solution
Free BrainMass Quizzes
Business Processes
This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.
SWOT
This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.
Organizational Leadership Quiz
This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.
Managing the Older Worker
This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce
Paradigms and Frameworks of Management Research
This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.