Draw a project network from the following information:
Activity Predecessor Duration
a none 2
b a 4
c a 3
d a 2
e b 3
f c 6
g c d 5
h e f 6
i g 5
j h i 5
Activities b and h can be shortened to a minimum of 2 weeks. Which activity would you shorten to reduce the project duration by 2 weeks? WHY? Must show critical path.
Purchase this Solution
Solution Summary
The expert examines drawing a project network from information.
Purchase this Solution
Free BrainMass Quizzes
Business Processes
This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.
MS Word 2010-Tricky Features
These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.
Lean your Process
This quiz will help you understand the basic concepts of Lean.
Marketing Management Philosophies Quiz
A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.
SWOT
This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.