Draw a project network from the following information

Not what you're looking for?

Ask Custom Question

Draw a project network from the following information:
Activity Predecessor Duration
a none 2
b a 4
c a 3
d a 2
e b 3
f c 6
g c d 5
h e f 6
i g 5
j h i 5

Activities b and h can be shortened to a minimum of 2 weeks. Which activity would you shorten to reduce the project duration by 2 weeks? WHY? Must show critical path.

Purchase this Solution

Solution Summary

The expert examines drawing a project network from information.

Purchase this Solution


Free BrainMass Quizzes
Business Processes

This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.

MS Word 2010-Tricky Features

These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.

Lean your Process

This quiz will help you understand the basic concepts of Lean.

Marketing Management Philosophies Quiz

A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.

SWOT

This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.