Please make sure to include the decision tree. File is attached.

1. Draw the complete detail of a network diagram corresponding to the following information.

a. What is the critical path for this project?
b. Suppose activity D can be shortened from four days to one day. Assume all other activity times remain the same. How much shorter will the total project earliest completion time become?
c. Suppose activity I is delayed, taking eight days to complete instead of two days. Assume all other activity times remain the same. How much longer will the total project earliest completion time become?
d. What is the latest start time for activity A?

Attachments
Purchase this Solution

Solution Summary

The solution assists with answering the questions regarding the network diagram.

Solution provided by:
Education
  • BE, Bangalore University, India
  • MS, University of Wisconsin-Madison
Recent Feedback
  • "Your explanation to the answers were very helpful."
  • "What does 1 and 0 means in the repair column?"
  • "Went through all of the formulas, excellent work! This really helped me!"
  • "try others as well please"
  • "Thank you, this helped a lot. I was not sure how to plug in those numbers to a formula. This was a great help. Now I have to figure out how to explain cost of capital is used in net present value analysis, and how cost of capital is used in net present value analysis. This stuff gets confusing."
Purchase this Solution


Free BrainMass Quizzes
Employee Orientation

Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.

Change and Resistance within Organizations

This quiz intended to help students understand change and resistance in organizations

Business Processes

This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.

Motivation

This tests some key elements of major motivation theories.