Poderosa Construction has budgeted $350,000 to build a new clubhouse. They use a mixture of union and nonunion personnel. Grading of the land, electrical, and plumbing work is subcontracted out to union shops. The actual construction of the project, though supervised by union carpenters, is performed mainly by nonunion laborers to conserve costs. Project planning has produced the following chart:

(See attachment)

(a) Use the critical path method (CPM) to calculate the earliest start and finish times for all
activities (forward pass) and the latest start and finish times for all activities (backward pass). (b) Compute the slack time for each activity and identify the critical activities.
(c) Identify all critical path(s). What is the project completion time?
(d) How long can the activity (C): "Hire nonunion labor" be delayed without delaying the
minimum completion time of the whole project?
(e) If activities (D) and (H) are each delayed by 3 days, how long will the whole project be
delayed?
(f) If activity (K) is delayed by 3 days, how long will the whole project be delayed?
(g) If activity (D) is delayed by 1 day (that is the duration of activity (D) changes from 8 days to 9 days and completion times of all other activities remain the same), how many critical paths do we have now in the whole project? What are they?

Attachments
Purchase this Solution

Solution Summary

This Solution provides the critical path for the given scenario.

Purchase this Solution


Free BrainMass Quizzes
Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

Understanding Management

This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.

Basic Social Media Concepts

The quiz will test your knowledge on basic social media concepts.

Six Sigma for Process Improvement

A high level understanding of Six Sigma and what it is all about. This just gives you a glimpse of Six Sigma which entails more in-depth knowledge of processes and techniques.

Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce