Explore BrainMass

Explore BrainMass

    Resource Allocation/Leveling

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Resource Allocation/Leveling

    Activity Duration Predecessors Personnel / Cost
    A 3 Days -- 1 Systems Analyst/$260 day
    B 6 Days -- 2 Programmers/$200 day each
    C 3 Days A 2 Programmers/$200 day each
    D 3 Days B 2 Hardware Specialists/$280 day each
    E 3 Days B 1 Hardware Specialist/$280 day
    F 2 Days C, D 1 Test Engineer/$300 day

    Personnel Available Quantity
    Systems Analysts 1
    Programmers 4
    Hardware Specialists 2
    Test Engineers 1

    Only the above personnel are currently available for the project but additional personnel can be hired at a 90% cost premium if needed.

    (a) What are the resource conflicts in the above project, if any. State the activities involved, the time frame of the conflict(s), the personnel in conflict and the number of people involved.

    (b) Note that operations cannot be split; what is the least cost method of resolving the conflict(s), assuming the project duration must not be extended? What additional cost, if any, will be incurred?

    © BrainMass Inc. brainmass.com June 4, 2020, 3:14 am ad1c9bdddf
    https://brainmass.com/business/human-resources-management/resource-allocation-leveling-504780

    Solution Preview

    Please see attachments for full solutions.

    Based on the updated Gantt Chart, we can see that a hardware specialist, wherein 2 are assigned to the project, has a conflict. This hardware specialist is assigned to Activities D and E at the same ...

    Solution Summary

    The solution discusses resource allocation and leveling.

    $2.19

    ADVERTISEMENT