Explore BrainMass

Valuation of the Silver Zuma project

1. What is the total cost of the Silver Zuma Project?
2. How much is needed in the first three months (January, February, and March)? (cash flow report)
3. Which if any of the resources are overallocated?
4. Assume that the project is time constrained (must be finished on time) and try to resolve any overallocation problems by leveling within slack. Will this resolve overallocation?
5. Assume that the project is resource constrained and no additional personnel are available. How long will the project take given the resources assigned? (Hint: Undo leveling performed in question 4 before answering this question.) Note: No splitting of activities is allowed.


Solution Summary

Discusses project time restraints.