Purchase Solution

Determining Project Information using Microsoft Project

Not what you're looking for?

Ask Custom Question

Silver Zuma Project

The ARC Company specializes in developing and selling a wide range of high-quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC's president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.

You are a member of a project team assigned to develop the new razor scooter code named "Silver Zuma." Table 1 contains the information necessary to create a project schedule. For the purpose of this case assume the following:

Part A.

1. The project begins January 6, 2014.
2. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
3. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off.
4. The project team works eight-hour days, Monday through Friday.

Table 1 - Silver Zuma Project

ID Task Name Duration Predecessors
1 Product development project
2 Market analysis 25 days
3 Product design 40 days 2
4 Manufacturing study 20 days 2
5 Product design selection 10 days 3,4
6 Detailed marketing plans 15 days 5
7 Manufacturing process 30 days 5
8 Detailed product design 50 days 5
9 Test prototype 10 days 8
10 Finalized product design 25 days 7,9
11 Order components 7 days 10
12 Order production equipment 14 days 10
13 Install production equipment 25 days 11FS + 20days
12FS + 40 days
14 Celebrate 1 day 13

Silver Zuma Project

Set up this project in MS Project 2010 and answer the following questions:

1. When is the project estimated to be completed (date)? How long will the project take (days)?
2. What is the critical path for the project? (identify by task numbers)
3. Which activity has the greatest amount of free slack?
4. Compare the advantages/disadvantages of displaying the schedule as a network versus a Gantt chart.

1. When is the project estimated to be completed (date)? How long will the project take (days)?
Finish Date: ?? / ?? / ????? Duration: _______ Days

2. What is the critical path for the project? (identify by task numbers)
Critical Path:

3. Which activity has the greatest amount of free slack?
Activity Name: Days: ______

4. Compare the advantages/disadvantages of displaying the schedule as a network versus a Gantt chart.

Attachments
Purchase this Solution

Solution Summary

Microsoft Project is used to determine the total length of the project and critical path. The gantt chart is used to determine the task with the highest amount of slack time. Also, the a review of the advantages of viewing the project scheduling in the gantt chart or the network view.

Solution Preview

The response is attached.

Silver Zuma Project - Part I

The ARC Company specializes in developing and selling a wide range of high-quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC's president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.

You are a member of a project team assigned to develop the new razor scooter code named "Silver Zuma." Table 1 contains the information necessary to create a project schedule. For the purpose of this case assume the following:

Part A.

1. The project begins January 6, 2014.
2. The following holidays are ...

Purchase this Solution


Free BrainMass Quizzes
Lean your Process

This quiz will help you understand the basic concepts of Lean.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

Writing Business Plans

This quiz will test your understanding of how to write good business plans, the usual components of a good plan, purposes, terms, and writing style tips.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce