Purchase Solution

CPM: What would be considered the Critical Path?

Not what you're looking for?

Ask Custom Question

In any project, what would be considered the Critical Path? The Critical Path does not mean technical criticality (as in risk), it means zero float. Critical Path Method (CPM).

Explain Discrete, Apportioned, and Level of Effort as the kind of work one produces.

What are some techniques used in workplaces for loading / leveling resources? Did these techniques work?

Purchase this Solution

Solution Summary

The 1473 word solution presents a very thorough explanation together with a network diagram of the critical path for any project plan.

Solution Preview

Please see the attached file.
In any project, what would be considered the Critical Path? The Critical Path does not mean technical criticality (as in risk), it means zero float. Critical Path Method (CPM).

A critical path in any project plan is the longest path in the project network diagram based on the predecessor/successor tasks and time estimates. Because it is the longest path, any delay in the critical path would create a delay in the project. For example, in the below network diagram, the critical path is 8 days and made of Tasks 1 and 2. If Task 2 takes 4 days (delayed) instead of 3 days, the project now takes 9 days to complete versus the original 8 days: (i.e. there will be a delay for the whole project)

Reason why it's called ZERO FLOAT is because, in every project, no matter how complicated, there are always some activities that can be started earlier or completed later without jeopardizing the final completion date for the project. This flexibility between the earliest time an activity can be completed and the latest time when it must be completed is called "float."

If an activity has flexibility (or float as you may call it) associated with its starts and ends, then this activity is not on the critical path, because the critical path refers to the sequence of activities from project start to end that bump up back-to-back against each other without any float.

Any activities on critical path must be completed exactly as scheduled, for the entire project to be completed on schedule. In other words, it is the longest sequence of activities with zero float. If any activity on the critical path is late, the entire project will be late (unless the time can be made up somewhere else on the critical path).

Q: Explain Discrete, Apportioned, and Level of Effort as the kind of work one produces

First it is useful for you to know that program management may provide a standard Project Work Plan template that contains tasks and an estimating model. If this has not been provided, or if the project is executed out of the context of program management, the project manager should perform some of the program-level activities, such as tailoring the Project Work Plan approach.

Program management typically provides project managers with the ...

Purchase this Solution


Free BrainMass Quizzes
Introduction to Finance

This quiz test introductory finance topics.

Paradigms and Frameworks of Management Research

This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.

Business Ethics Awareness Strategy

This quiz is designed to assess your current ability for determining the characteristics of ethical behavior. It is essential that leaders, managers, and employees are able to distinguish between positive and negative ethical behavior. The quicker you assess a person's ethical tendency, the awareness empowers you to develop a strategy on how to interact with them.

Understanding the Accounting Equation

These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.

Operations Management

This quiz tests a student's knowledge about Operations Management