A project is being analyzed using PERT. The expected completion time of the project is 70 weeks with a standard deviation of 5 weeks. Assume the project completion time is normally distributed. If the due date of the project is to be set to there is only a 20% chance of being late (and an 80% chance of finishing on time), what should the due date be?
a. 71.00
b. 74.00
c. 65.79
d. 74.21
Purchase this Solution
Solution Summary
The expected completion time is expressed in order to determine due date in this case.
Solution Preview
19) Let X be the number of weeks that it takes to complete the project. So X is normally ...
Purchase this Solution
Free BrainMass Quizzes
Terms and Definitions for Statistics
This quiz covers basic terms and definitions of statistics.
Measures of Central Tendency
This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.
Know Your Statistical Concepts
Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.
Measures of Central Tendency
Tests knowledge of the three main measures of central tendency, including some simple calculation questions.