    The following information has been gathered for a project:

    TIME ESTIMATES (DAYS)
    Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic
    A ---- 6 9 12
    B ---- 4 8 12
    C A 5 6 7
    D A 2 4 6
    E B,D 4 7 10

    What is the expected completion time of the project?
    Select one:
    a. 34
    b. 15
    c. 20
    d. 25

    What is the probability of completing the project given in 22 days?
    Select one:
    a. greater than 95%
    b. greater than 75% but less than or equal to 85%
    c. greater than 85% but less than or equal to 95%
    d. less than or equal to 75%.

    © BrainMass Inc. brainmass.com June 4, 2020, 4:23 am ad1c9bdddf
    https://brainmass.com/business/business-management/calculating-expected-completion-time-559257

    Solution Summary

    Solution depicts the steps to calculate expected completion time. It also calculates the and desired probability value.

    $2.19

    ADVERTISEMENT