    Calculating Probability for Completing a Project

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Using the information provided in the table, the network diagram and the expected project completion time = 39 weeks (see attachment):

    The critical path is A-B-D-G-H.

    (a) Calculate the probability of completing the project in 36 weeks.

    P(project ? 36) =

    (b) Calculate the probability of completing the project in 40 weeks.

    P(project ? 40) =

    (Round your answers to 3 decimal places, the tolerance is +/-0.005).

    © BrainMass Inc. brainmass.com October 10, 2019, 5:13 am ad1c9bdddf
    https://brainmass.com/business/business-math/calculating-probability-completing-project-497454

    Attachments

    Solution Preview

    Please see attachment for proper formatting.

    (a) Calculate the probability of completing the project in 36 weeks.

    Task / Optimistic time / Probable time / Pessimistic time / Expected ...

    Solution Summary

    The solution provides the calculations for the probability of completing a project.