    The following information has been gathered for a project:
    TIME ESTIMATES (DAYS)
    Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic
    A ---- 6 9 12
    B ---- 4 8 12
    C A 5 6 7
    D A 3 5 7
    E B,D 4 7 10

    What is the probability of completing the project given in Question 9 in 23 days, using the critical path?
    Select one:

    a. Greater than 85% but less than or equal to 95%
    b. Less than or equal to 75%
    c. Greater than 75% but less than or equal to 85%
    d. Greater than 95%