Given an auditing project with the following activities,

Using the critical path, find:

(a)The probability of completing this project in 12 weeks (or less), as the client desires.
(b)The probability of completing this project in 13 weeks (or less).
(c)The probability of completing this project in 16 weeks (or less), the clients drop dead date.
(d)The number of weeks required to assure a 92.5 percent chance of completion, a guaranteed by the auditing firm.

© BrainMass Inc. brainmass.com October 24, 2018, 8:14 pm ad1c9bdddf
https://brainmass.com/business/business-management/pdm-cpm-chart-91373

Attachments

Solution Summary

Solution shows calculations of:
(a) The probability of completing this project in 12 weeks (or less), as the client desires.
(b) The probability of completing this project in 13 weeks (or less).
(c) The probability of completing this project in 16 weeks (or less), the clients drop dead date.

$2.19
See Also This Related BrainMass Solution

PDM/CPM Chart

The following network is a compressed representation of the prospectus of a start-up firm that plans to develop a new, bio-electronic computer chip.

Note that four activities, the biological elements, can start immediately.

Find:
(a) The critical path
(b) The earliest time to complete the project
(c) The slack on activities E, F, and H.

View Full Posting Details