    PDM/CPM Chart and Critical Path

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    The following network is a compressed representation of the prospectus of a start-up firm that plans to develop a new, bio-electronic computer chip.

    Note that four activities, the biological elements, can start immediately.

    Find:
    (a) The critical path
    (b) The earliest time to complete the project
    (c) The slack on activities E, F, and H.

    © BrainMass Inc. brainmass.com June 3, 2020, 7:14 pm ad1c9bdddf
    https://brainmass.com/business/business-management/pdm-cpm-chart-critical-path-91375

    Attachments

    Solution Preview

    WHAT IS THE CRITICAL PATH?

    To find the critical path, we need to determine the following quantities for each activity in the
    network.

    1. Earliest start time (ES): the earliest time an activity can begin without violation of immediate
    predecessor requirements
    2. Earliest finish time (EF): the earliest time at which an activity can end
    3. Latest start time (LS): the latest time an activity can begin without delaying the entire project
    4. Latest finish time (LF): the latest time an activity can end without delaying the entire project

    We begin at network's origin, START, to compute the earliest start time (ES) and earliest finish
    time (EF) for each activity. For the first ...

    Solution Summary

    This solution is comprised of a detailed explanation to find the critical path, the earliest time to complete the project, and the slack on activities E, F, and H.