Explore BrainMass

Explore BrainMass

    WBS for CRM Implementation in MS Projects

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    In the past you created a work breakdown structure for the entire CRM system implementation. You also elaborated on that structure and identified more details for one of the deliverables. In the past you also created a schedule for the training deliverables. You also identified the skills you needed for a team. Now, as a team, you will create a fully leveled schedule for the entire project (CRM implementation, marketing program, and training). The schedule should be created in Microsoft Project. you will first need to define the following:

    *set-up of Microsoft Project (including how you will work on the file individually and jointly)
    *phases
    *deliverables from each phase
    *milestones in each phase
    *skills required for each team
    *resources available to the project with the given skills
    *availability of each resource to the project (doesn't forget about vacations, *training, holidays, etc.)

    Make sure you document the resource descriptions (skills and availability) in a simple format for the instructor.

    Then,as a team, divide the project schedule into sections. Do NOT divide the resources/assign them to be used by only one team member. As individual team members (example: Team member A, B, etc.) complete the schedule for the assigned section.

    *Provide more detail by defining the tasks.
    *Assign dependencies among tasks, including lead and lag time.
    *Assign resources to tasks based on the skills and availability defined by the team.
    *Level each team members of the project.
    *Conduct a PERT analysis for one section of the team members schedule.
    *Create a baseline for each team members section of the project.

    As a Team complete the following steps to finish the project schedule:

    *Combine the individual plans into one plan (if needed).
    *Review and refine the critical path.
    *Identify dependency and resource conflicts.
    *Level the entire project to the extent that makes sense (remember that the *project has to be complete within a nine-month period and other interim dates *were defined in the past).
    *Create a baseline for the entire project.
    *As you adjust the schedule to meet the required dates, document the trade-offs *you made and the risks introduced by those trade-offs. (If you do not have to *make any trade-offs because you can meet the timeframes, turn in the schedule, *resourece descriptions, and trade-off descriptions ). Be sure to explain which *point of view(s) is best for evaluating the project schedule, including the PERT values.

    © BrainMass Inc. brainmass.com June 3, 2020, 6:41 pm ad1c9bdddf
    https://brainmass.com/business/project-management/wbs-crm-implementation-ms-projects-70435

    Solution Preview

    Hi,

    Please find attached the solution to the integrated project plan. There are a couple of files that I need to share with you. Hence, ...

    Solution Summary

    This posting provides Project Plan (WorkBreakdown structure) for implementation of CRM System using MS Projects

    $2.19

    ADVERTISEMENT