2. Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17 week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times.

Activity Immediate Predecessor Time
(weeks)
A -- 3
B -- 1
C -- 2
D A,B,C 4
E C,D 5
F A 3
G D,F 6
H E 4

a. Prepare a project network.
b. Identify the critical activities.
c. Which activity has the most slack time?
d. Will the project be completed by September 1?

Solution Preview

2. Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17 week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times.

Activity Immediate ...

Solution Summary

Project networks, PERT, critical activities and slack time are investigated.