Please help me to solve the following problem:

You are working on a project that has 12 activities. You determine that the critical path consists of only five activities. You then compute the variances for the five critical path activities and these variances are 3, 4, 2, 1, and 6 days. The desired completion date for the project is 44 days and the expected completion date for the project is 40 days. Which of the alternatives gives the probability that the project will be completed by the desired completion date?

Thank you.

Purchase this Solution

Solution Summary

Provides steps necessary to determine probability.

Solution Preview

Variance for the critical path = 3+4+2+1+6=16
Standard deviation for the critical path = 16^0.5=4 days

Assuming normal distribution of the ...

Purchase this Solution


Free BrainMass Quizzes
Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce

SWOT

This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.

Business Processes

This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.

Academic Reading and Writing: Critical Thinking

Importance of Critical Thinking

Change and Resistance within Organizations

This quiz intended to help students understand change and resistance in organizations