    PERT/CPM Computation

    Not what you're looking for? Search our solutions OR ask your own Custom question.

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Activity Duration Precedes
    A (start) 1 B, C
    B 1 E
    C 4 F
    D 2 F
    E 2 _
    F (end)

    1. Draw an AON diagram of the project, including activity durations.
    2. Define the critical path, listing all critical activities in chronological order.
    3. What is the project duration (in weeks)?
    4. What is the slack (in weeks) associated with any, and all non-critical paths through the project?

    © BrainMass Inc. brainmass.com March 4, 2021, 11:28 pm ad1c9bdddf
    https://brainmass.com/business/business-management/pert-cpm-computation-425153

    Solution Preview

    A summary of the response:

    ? The computed project's duration is seven ...

    Solution Summary

    This solution gives a detailed computation of PERT/CPM problem.