Crashing Cost
Not what you're looking for?
{Act.} {Normal time} {Crash Time} {Normal Cost} {Crash Cost} {Immed. Pred.}
(days) (Days)
A 6 5 $900 1,000 -
B 8 6 300 400 -
C 4 3 500 600 -
D 5 3 900 1,200 A
E 8 5 1,000 1,600 C
What is the minimum cost of crashing the following project by 4 days?
Purchase this Solution
Solution Summary
The solution answers the question below and goes into some detail as well. The solution is ideal for students who are looking for a short answer to the question.
Solution Preview
Activity Crashed Cost
C 100
A ...
Purchase this Solution
Free BrainMass Quizzes
SWOT
This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.
Six Sigma for Process Improvement
A high level understanding of Six Sigma and what it is all about. This just gives you a glimpse of Six Sigma which entails more in-depth knowledge of processes and techniques.
Learning Lean
This quiz will help you understand the basic concepts of Lean.
Business Processes
This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.
Transformational Leadership
This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.