Problem on project crashing

What is the minimum cost of crashing the following project by 4 days?

Normal Crash Normal Crash Immediate
Activity Time (days)Time (days) Cost Cost Predecessor(s)

A 6 5 $ 900 $1,300 ?
B 8 6 300 800 ?
C 4 3 500 700 ?
D 5 3 900 1,900 A
E 8 5 1,000 1,900 C