Calculating normal and standard time for a task

Not what you're looking for?

Ask Custom Question

Peter Rourke, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. The allowances for tasks such as tis are personal. 7%; fatigue, 10%; and delay, 3%

TASK PERFORMANCE OBSERVATIONS (MINUTES)
ELEMENT RATING (%) 1 2 3 4 5

1 110 5 4 6 4 4
2 95 6 8 7 6 7
3 90 6 4 7 5 5
4 85 1.5 1.8 2.0 1.7 1.5

a) What is the normal time?
b) What is the standard time?

Attachments
Purchase this Solution

Solution Summary

This solution depicts the steps to estimate the normal and standard time for the given task.

Solution Preview

a) What is the normal time?

Average observed time for task element 1=(5+4+6+4+4)/5=4.60 minutes
Average observed time for task element 2=(6+8+7+6+7)/5=6.80 minutes
Average observed time for task element 3=(6+4+7+5+5)/5=5.40 ...

Solution provided by:
Education
  • BEng (Hons) , Birla Institute of Technology and Science, India
  • MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
  • "Thank you"
  • "Really great step by step solution"
  • "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
  • "Thanks Again! This is totally a great service!"
  • "Thank you so much for your help!"
Purchase this Solution


Free BrainMass Quizzes
Situational Leadership

This quiz will help you better understand Situational Leadership and its theories.

Introduction to Finance

This quiz test introductory finance topics.

IPOs

This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)

Marketing Research and Forecasting

The following quiz will assess your ability to identify steps in the marketing research process. Understanding this information will provide fundamental knowledge related to marketing research.

Lean your Process

This quiz will help you understand the basic concepts of Lean.