    Calculating Standard Time for Servicing Sundae

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    The industrial engineer for an ice cream chain is performing a time study to determine the standard time for serving sundaes to customers. He times 10 cycles of the task and records the observations on the table below:

    The engineer rated the pace of elements 1 and 4 (pick up cup, and hand to customer) at 100%, and the other 2 elements at 90%. The PR&D (personal, rest, and delay) allowance is 13%.

    Compute the standard of the task (servicing sundae).

    Equations:

    NT (normalized Time)
    = ET (Elemental Time)
    x RF (Rating Factor)

    Standard Time = ∑NT (normalized Time) x (1 + PR&D)

    (see chart in attached file)

    © BrainMass Inc. brainmass.com June 3, 2020, 6:55 pm ad1c9bdddf
    https://brainmass.com/business/business-management/calculating-standard-time-servicing-sundae-79205

    Attachments

    Solution Summary

    The industrial engineer for an ice cream chain is performing a time study to determine the standard time for serving sundaes to customers. The solution gives calculations on how ti get standard time.

    $2.19

    ADVERTISEMENT