    The following activities are part of a project to be scheduled using CPM:

    (see chart in attached file)

    Draw the network.
    What is the critical path?
    How many weeks will it take to complete the project?
    How much slack does activity B have?

    The following activities are part of a project to be scheduled using CPM:

    ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
    A — 6
    B A 3
    C A 7
    D C 2
    E B, D 4
    F D 3
    G E, F 7

    Draw the network.
    What is the critical path?
    How many weeks will it take to complete the project?
    How much slack does activity B have?