    Critical Path Method (CPM)

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Schedule the following activities using the CPM.

    Activity Intermediate Predecessor Time (weeks)
    A - 1
    B A 4
    C A 3
    D B 2
    E C,D 5
    F D 2
    G F 2
    H E,G 3

    a) Draw the network.
    b) What is the critical path?
    c) How many weeks will it take to complete this project?
    d) Which activities have slack and how much?