1. Mrs. Tolstoy and her husband, Serge, are planning their dream house. The lot for the house sits high on a hill with a beautiful view of the Appalachian Mountains. The plans for the house show the size of the house to be 2,900 square feet. The average price for a lot and house similar to this one has been $120 per square foot. Fortunately, Serge is a retired plumber and feels he can save money by installing the plumbing himself. Mrs. Tolstoy feels she can take care of the interior decorating.
The following average cost information is available from a local bank that makes loans to local contractors and disperses progress payments to contractors when specific tasks are verified as complete.

24% Excavation and framing complete

8% Roof and fireplace complete

3% Wiring roughed in

6% Plumbing roughed in

5% Siding on

17% Windows, insulation, walks, plaster, and garage complete

9% Furnace installed

4% Plumbing fixtures installed

10% Exterior paint, light fixtures installed, finish hardware installed

6% Carpet and trim installed

4% Interior decorating

4% Floors laid and finished

A. What is the estimated cost for the Tolstoy's house if they use contractors to complete all of the house?

B. Estimate what the cost of the house would be if the Tolstoys use their talents to do some of the work themselves.

2. Below is a project WBS with cost apportioned by percents. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables?

A. Design?

B. Programming?

C. In-house testing?

What weaknesses are inherent in this estimating approach?

Exercise 5.2 WBS Figure

3. Firewall Project XT. Using the 'complexity weighting' scheme shown in Table 5.2 and the function point complexity weighted table shown below, estimate the total function point count. Assume historical data suggest five function points equal one person a month and six people can work on the project.

Complexity Weight Table

Number of inputs 10 Rated complexity low

Number of outputs 20 Rated complexity average

Number of inquires 10 Rated complexity average

Number of files 30 Rated complexity high

Number of interfaces 50 Rated complexity high

A. What is the estimated project duration?
B. If 20 people are available for the project, what is the estimated project duration?
C. If the project must be completed in six months, how many people will be needed for the project?

Attachments
Purchase this Solution

Solution Summary

The solution discusses the average cost information to plan a dream home.

Solution provided by:
Education
  • BE, Bangalore University, India
  • MS, University of Wisconsin-Madison
Recent Feedback
  • "Your explanation to the answers were very helpful."
  • "What does 1 and 0 means in the repair column?"
  • "Went through all of the formulas, excellent work! This really helped me!"
  • "try others as well please"
  • "Thank you, this helped a lot. I was not sure how to plug in those numbers to a formula. This was a great help. Now I have to figure out how to explain cost of capital is used in net present value analysis, and how cost of capital is used in net present value analysis. This stuff gets confusing."
Purchase this Solution


Free BrainMass Quizzes
Business Ethics Awareness Strategy

This quiz is designed to assess your current ability for determining the characteristics of ethical behavior. It is essential that leaders, managers, and employees are able to distinguish between positive and negative ethical behavior. The quicker you assess a person's ethical tendency, the awareness empowers you to develop a strategy on how to interact with them.

Understanding the Accounting Equation

These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.

Lean your Process

This quiz will help you understand the basic concepts of Lean.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce