Explore BrainMass

Explore BrainMass

    Network activity chart

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Develop the network activity chart and identify the critical path for a project based on the information provided below:

    Activity.......Expected Duration (days).......Predecessor
    A...............................5....................................----
    B..............................10....................................A
    C...............................8.....................................A
    D...............................1.....................................A
    E...............................5....................................B,C
    F..............................10...................................D,E
    G..............................14....................................F
    H...............................3.....................................G
    I................................12....................................F
    J................................6.....................................H,I

    1. Draw the activity network as a Gantt chart.
    2. What is the expected duration of the project?

    © BrainMass Inc. brainmass.com June 4, 2020, 3:41 am ad1c9bdddf
    https://brainmass.com/business/business-management/network-activity-chart-529058

    Solution Preview

    Please see attachment for complete solution.

    Activity Expected Duration Predecessor
    A 5 days ----
    B 10 days A
    C 8 days A
    D 1 day A
    E 5 days B, C
    F 10 days D, E
    G 14 days F
    H 3 days G
    I 12 days F
    j 6 days H, I

    5
    5 days ...

    Solution Summary

    The network activity chart are examined.

    $2.19

    ADVERTISEMENT