    Guidance appreciated on my efforts to create the network diagram.

    Construct a network and determine the expected completion time

    Preceding
    Activity (weeks) Te Activities
    a 3 None
    b 5 a
    c 3 a
    d 1 c
    e 3 b
    f 4 b, d
    g 2 c
    h 3 g, f
    i 1 e, h