    Determine critical path and also need help in finding how to reduce the project time by a number of weeks.

    Activity Immediate Predecessor Time (in weeks)
    A none 4
    B A 2
    C A 4
    D A 3
    E B,C 5
    F C 6
    G D 2
    H E 3
    I F,G 5
    J H,I 7

    1. Draw the network diagram.
    2. Find the critical path.
    3. If activities A and J can't be shortened, yet activities B through I can be shortened to a minimum of one week at a price of $10,000 per week, which activities would you shorten to cut the project by four weeks?