    Calculations Using ETC, BAc, BCWP, EAC

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    1) Provide and show all answers and step by step work to obtain answer not skipping any steps, show all equations, acronyms (ie ETC, ACWP, etc), and if applicable, a description of how came to the answer.

    Problem:

    Bob's ETC = 6000, BAc = 10,000, BCWP=4,800, EAC = 14,000. What has Bob spent to date?

    Ans = 8000, but why, show steps to solve, etc as I asked.

    © BrainMass Inc. brainmass.com June 4, 2020, 3:23 am ad1c9bdddf
    https://brainmass.com/business/business-management/calculations-bac-bcwp-eac-512348

    Solution Preview

    ETC (Estimate to Complete) is the expected cost needed to complete the remaining steps in the project.
    BCWP (Budgeted cost of work performed) or EV (earned ...

    Solution Summary

    The solution determines calculation using ETC, BAc, BCWP and EAC.