    1) Provide and show all answers and step by step work to obtain answer not skipping any steps, show all equations, acronyms (ie ETC, ACWP, etc), and if applicable, a description of how came to the answer.

    Problem:

    John's BCWP=42, ACWP=42, BAC=60, EAC=?

    © BrainMass Inc. brainmass.com June 4, 2020, 3:23 am ad1c9bdddf
    https://brainmass.com/business/business-management/bcwp-acwp-bac-eac-512347

    Solution Preview

    BCWP (Budgeted cost of work performed) or EV (earned value) is the budgeted cost of work that was performed during the scheduled task.

    ACWP ...