Explore BrainMass

Explore BrainMass

    IT Project Management Calculations

    Not what you're looking for? Search our solutions OR ask your own Custom question.

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Assume you have completed three months of the project. The BAC was $200 000 for this six month project. Also assume the following:

    PV = $120,000
    EV = $100,000
    AC = $90,000

    A. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

    B. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

    C. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

    © BrainMass Inc. brainmass.com March 4, 2021, 9:37 pm ad1c9bdddf
    https://brainmass.com/business/project-management/it-project-management-calculations-258691

    Solution Preview

    IT Project Management
    Assume you have completed three months of the project. The BAC was $200 000 for this six month project. Also assume the following:

    PV = $120,000
    EV = $100,000
    AC = $90,000

    A. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

    B. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

    C. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
    ===============================================================================
    BAC (Budget at Completion) - $200,000
    ? the ...

    Solution Summary

    Discussion and calculation of various Project Management Variables: Cost variance, Schedule Variance, Cost Performance Index (CPI), Schedule Performance Index (SPI), Estimate at Completion (EAC).

    $2.49

    ADVERTISEMENT