You are budgeted to spend $2,000,000 in burdened labor and $800,000 in material. At the end of the first month of your project, the following information is made available:

Labor:

•ACWP = $ 80,000.
•BCWP = $ 90,000.
•BAC = $2,000,000.

Material:

•ACWP = $ 500,000.
•BCWP = $ 350,000.
•BAC = $ 800,000.

Determine the estimated cost at completion for both Labor and Material.

Purchase this Solution

Solution Summary

This solution illustrates how to compute the estimated cost at completion for both Labor and Material.

Solution Preview

Estimated cost at completion (EAC) = Budget at completion (BAC)/Cost performance index (CPI)
CPI = Actual cost of work performed (ACWP) ...

Purchase this Solution


Free BrainMass Quizzes
Lean your Process

This quiz will help you understand the basic concepts of Lean.

Academic Reading and Writing: Critical Thinking

Importance of Critical Thinking

Introduction to Finance

This quiz test introductory finance topics.

Transformational Leadership

This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.

Six Sigma for Process Improvement

A high level understanding of Six Sigma and what it is all about. This just gives you a glimpse of Six Sigma which entails more in-depth knowledge of processes and techniques.