    21. Given the following network with activities and times estimated in days.

    (see attached file for diagram and chart)

    Activity
    Optimistic Most Probable
    Pessimistic
    A 2 5 6
    B 1 3 7
    C 6 7 10
    D 5 12 14
    E 3 4 5
    F 8 9 12
    G 4 6 8
    H 3 6 8
    I 5 7 12
    J 12 13 14
    K 1 3 4

    a. What are the critical path activities?
    b. What is the expected time to complete the project?
    c. What is the probability the project will take more than 28 days to complete?

    © BrainMass Inc. brainmass.com June 3, 2020, 7:09 pm ad1c9bdddf
    https://brainmass.com/statistics/probability/pert-network-critical-path-activities-87927

    Attachments

    Solution Summary

    Given the network with activities and times estimates the solution finds out the critical path activities, calculates the expected time to complete the project and the probability the project will take more than 28 days to complete.