P chart - Is the process out of control?

Not what you're looking for?

Ask Custom Question

A p-chart has been developed for a particular item. In the past, 3% of such items have been found to be defective. If a sample of 100 is taken, and 9 of these are found to be defective, should the process be considered out of control? Explain

Purchase this Solution

Solution Summary

The expert examines if the process is out of control using a p-chart. A complete, neat and step-by-step solution is provided.

Solution Preview

p = 0.03, n = 100

Standard error, SE = sqrt[p(1 - p)/n] = sqrt[0.03(1 - 0.03)/100] = ...

Purchase this Solution


Free BrainMass Quizzes
Measures of Central Tendency

Tests knowledge of the three main measures of central tendency, including some simple calculation questions.

Terms and Definitions for Statistics

This quiz covers basic terms and definitions of statistics.

Know Your Statistical Concepts

Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.

Measures of Central Tendency

This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.