    TRANSPORTATION ASSIGNMENT

    The Marion Fruit Company has orange groves at three different sites throughout central Florida. It also has four plants for turning fruit into orange juice concentrate. The fruit must be picked and transported from the groves to the concentrate plant. The transportation costs depend directly upon the distances from the grove to the plant. The supply of oranges (in tons) at each grove and the capacity of each plant (also in tons) are shown along with the distances from each grove to each plant in the table below. Model this transportation problem as an IP model to find the minimum distance allocation of orange supply to concentrate plants. (10 points)

    Distance (miles) to Plant at
    Grove Ocala Orlando Leesburg Crystal River Supply
    Lynne 20 10 50 30 1000
    Eustis 70 40 10 80 1500
    Clermont 30 20 80 50 1250
    Demand 750 1100 1700 500

    © BrainMass Inc. brainmass.com October 10, 2019, 2:05 am ad1c9bdddf
    https://brainmass.com/math/linear-programming/transportation-linear-programming-problem-362313

    Attachments

    Solution Summary

    LP problem is integrated in this solution.

    $2.19