At the Hard Rock Cafe, like many organizations, project management is a key planning tool. With Hard Rock's constant growth in hotels and cafes, remodeling of existing cafes, scheduling for Hard Rock Live concert and event venues, and planning the annual Rockfest, managers rely on project management techniques and software to maintain schedule and budget performance.

"Without Microsoft Project," says Hard Rock Vice-President Chris Tomasso, "there is no way to keep so many people on the same page." Tomasso is in charge of the Rockfest event, which is attended by well over 100,000 enthusiastic fans. The challenge is pulling it off within a tight 9-month planning horizon. As the event approaches, Tomasso devotes greater energy to its activities. For the first 3 months, Tomasso updates his MS Project charts monthly. Then at the 6-month mark, he updates his progress weekly. At the 9- month mark, he checks and corrects his schedule twice a week.

Early in the project management process, Tomasso identifies 10 major tasks (called level 2 activities in a work breakdown structure, or WBS):talent booking, ticketing, marketing/PR, online promotion, television, show production, travel, sponsorships, operations, and merchandising. Using a WBS, each of these is further divided into a series of subtasks. The following table identifies 26 of the major activities and subactivities, their immediate predecessors, and time estimates. Tomasso enters all of these into the MS Project software. Tomasso alters the MS Project document and the time line as the project progresses. "It's okay to change it as long as you keep on track," he states.

Activity
Description
Predecessor
Normal Time (weeks)
Normal Cost
Crash Time (weeks)
Crash Cost

A
Finalize site and building contracts
---
7
$7,500
4
$11,500

B
Select local printer
A
3
$500
2
$800

C
Hire production manager
A
3
$1,200
2
$1,700

D
Design promotional Web site
B
5
$6,000
3
$9,000

E
Set TV deal
D
6
$4,000
4
$6,500

F
Hire director
E
4
$1,200
3
$1,700

G
Plan for TV camera placement
F
2
$500
2
$500

H
Target headline entertainers
B
4
$2,000
3
$3,500

I
Target support entertainers
H
4
$2,000
3
$3,500

J
Travel accommodations for talent
I
10
$9,000
7
$16,000

K
Set venue capacity
C
2
$300
1
$400

L
Ticketmaster contract
D
3
$1,400
2
$1,900

M
On-site ticketing
L
8
$7,000
6
$11,000

N
Sound and staging
C
6
$9,000
5
$12,000

O
Passes and stage credentials
G
7
$4,000
5
$5,800

P
Travel accommodations for staff
B
20
$15,000
15
$23,000

Q
Hire sponsor coordinator
B
4
$600
3
$800

R
Finalize sponsors
Q
4
$1,000
3
$1,400

S
Define/place signage for sponsors
R
3
$3,000
2
$4,200

T
Hire operations manager
A
4
$1,200
2
$1,800

U
Develop site plan
T
6
$6,000
5
$8,500

V
Hire security director
T
7
$1,500
5
$3,000

W
Set police/fire security plan
V
4
$1,000
3
$1,600

X
Power, plumbing, AC, toilet services
U
8
$4,000
6
$7,000

Y
Secure merchandise deals
B
6
$6,000
3
$7,500

Z
Online merchandise sales
Y
6
$5,000
4
$7,500

The day of the rock concert itself is not the end of the project planning. "It's nothing but surprises. A band not being able to get to the venue because of traffic jams is a surprise, but an 'anticipated' surprise. We had a helicopter on stand-by ready to fly the band in," says Tomasso.

On completion of Rockfest in July, Tomasso and his team have a 3-month reprieve before starting the project planning process again.

Source: Professor Barry Render, Jay Heizer and Beverly Amer.

Please turn in a paper of one to two pages (page counting does not include cover and reference list) discussing the following questions:

1. Identify the critical path and its activities for Rockfest. How long does the project take (what is the duration time)?

2. How would you crash the project (which activities would you crash) to keep the project on schedule and achieve the original duration, if Activity B actually takes 5 weeks instead of the planned 3 weeks? (Explain your logic)?

Purchase this Solution

Solution Summary

The problem deals with determining the duration of a project, its critical path, and crashing options.

Solution provided by:
Education
  • B. Sc., University of Nigeria
  • M. Sc., London South Bank University
Recent Feedback
  • "Thank you."
  • "thank you Chidi Ngene.. if you have any APA references would be great"
  • "Thank you so much for your help, your explanations were easy to understand and apply!"
  • "are you able to highlight the equations used either on the xlsx or a word doc as to how each graph was formed- overall looks fine i just need help understanding this myself"
  • "Chidi Ngene, M. Sc. Was extremely helpful as without the help and guidance I would have failed, but with the help I passed. I still have a lot to learn and in need of the guidance to understand and learn more on the subject. I would recommend Chidi Ngene and BrainMass to anyone that are in need of help. Thank you!!"
Purchase this Solution


Free BrainMass Quizzes
Transformational Leadership

This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.

Lean your Process

This quiz will help you understand the basic concepts of Lean.

Situational Leadership

This quiz will help you better understand Situational Leadership and its theories.

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.

Motivation

This tests some key elements of major motivation theories.