I am stuck on this... Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are $400 (19 time units), $350 (18), $300 (17), $25 (16) compute the total project cost for each duratin. Plot the total direct, indirect and project costs for each of these durations on a cost-time graph. What is the optimum cost-time schedule for the project and the cost?
ID Slope Maximum Normal Normal
Crash Time Time Cost
a 20 1 3 50
b 60 2 5 60
c 40 1 3 70
d 0 0 10 50
e 50 3 6 100
f 100 3 7 90
g 70 1 5 50
Purchase this Solution
Solution Summary
The solution computes the total direct cost for each project duration and plot the total direct, indirect and project costs for each of the duration.
Purchase this Solution
Free BrainMass Quizzes
Business Ethics Awareness Strategy
This quiz is designed to assess your current ability for determining the characteristics of ethical behavior. It is essential that leaders, managers, and employees are able to distinguish between positive and negative ethical behavior. The quicker you assess a person's ethical tendency, the awareness empowers you to develop a strategy on how to interact with them.
Lean your Process
This quiz will help you understand the basic concepts of Lean.
Business Processes
This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.
Paradigms and Frameworks of Management Research
This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.
Balance Sheet
The Fundamental Classified Balance Sheet. What to know to make it easy.