Project Management- Critical Path Method (CPM)

Not what you're looking for?

Ask Custom Question

Please see attached file for the table.

You have a network with a critical path A-B-C-D. For our purposes, you are allowed to ignore the other paths through the network. The values for optimistic (a), pessimistic (b) and most likely (m) durations for each task are as shown below. These are based on the probability that virtually all (at least 99.7%) of the values of each task fall within the range from a to b. (table)

a. What is the value of mean for the network?
b. What is the value of variance for the network?
c. What is the probability that this network can be finished within 27 days?

Attachments
Purchase this Solution

Solution Summary

Calculates probability of completion within a specified period in a network.

Purchase this Solution


Free BrainMass Quizzes
Operations Management

This quiz tests a student's knowledge about Operations Management

Academic Reading and Writing: Critical Thinking

Importance of Critical Thinking

Understanding Management

This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.

Learning Lean

This quiz will help you understand the basic concepts of Lean.

Employee Orientation

Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.