Project Management- Critical Path Method (CPM)

This content was STOLEN from BrainMass.com - View the original, and get the already-completed solution here!

Please see attached file for the table.

You have a network with a critical path A-B-C-D. For our purposes, you are allowed to ignore the other paths through the network. The values for optimistic (a), pessimistic (b) and most likely (m) durations for each task are as shown below. These are based on the probability that virtually all (at least 99.7%) of the values of each task fall within the range from a to b. (table)

a. What is the value of mean for the network?
b. What is the value of variance for the network?
c. What is the probability that this network can be finished within 27 days?

© BrainMass Inc. brainmass.com December 20, 2018, 8:07 am ad1c9bdddf
https://brainmass.com/business/business-math/project-management-critical-path-method-cpm-433219

Attachments

Solution Summary

Calculates probability of completion within a specified period in a network.

$2.19