A Critical path problem
Not what you're looking for?
Activity Immediate
predecessors Activity Times (days) Estimated activity time Critical Path Activity
a m b
A - 3 3 3
B - 1 2 4
C B 3 4 5
D A 2 5 8
E A 3 5 7
F C, E 1 2 3
G F 5 6 7
1. Draw the network, calculate activity times and determine the critical path and project time.
2. Calculate the standard deviation for the project time.
3. Determine the probability that the project will take in excess of 18 days, less than 15 days.
4. If we wanted a 90% probability of completion by a given date, how many days would we use as our target?
Purchase this Solution
Solution Summary
This posting contains solution to following problem on CPM.
Purchase this Solution
Free BrainMass Quizzes
Understanding Management
This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.
Academic Reading and Writing: Critical Thinking
Importance of Critical Thinking
Operations Management
This quiz tests a student's knowledge about Operations Management
Balance Sheet
The Fundamental Classified Balance Sheet. What to know to make it easy.
Change and Resistance within Organizations
This quiz intended to help students understand change and resistance in organizations