Finding the Critical Path in a Problem
Not what you're looking for?
According to the data in the table, what is the critical path?
Activity | Immediate Predecessor | Optimistic Time | Most Likely Time | Pessimistic Time
A - 2 8 14
B - 8 8 8
C A 9 9 18
D B 11 11 17
Options:
A, B
A, C
B, D
A, B, C, D
none of the above
Purchase this Solution
Solution Summary
Solution determines the critical path in the given case using a table and diagram along with brief explanation to aid understanding.
Solution Preview
Please refer attached file for better clarity of table and diagram.
Activity Analysis for Project Problem
Activity On Critical Activity Earliest Earliest Latest Latest Slack
Name ...
Education
- BEng (Hons) , Birla Institute of Technology and Science, India
- MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
- "Thank you"
- "Really great step by step solution"
- "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
- "Thanks Again! This is totally a great service!"
- "Thank you so much for your help!"
Purchase this Solution
Free BrainMass Quizzes
Measures of Central Tendency
This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.
Terms and Definitions for Statistics
This quiz covers basic terms and definitions of statistics.
Measures of Central Tendency
Tests knowledge of the three main measures of central tendency, including some simple calculation questions.
Know Your Statistical Concepts
Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.