The hickory company manufactures wooden desks. Management schedules overtime every weekend to reduce the backlog on the most popular models. The automatic routing machine is used to cut certain types of edges on the desktops the following orders need to be scheduled for the routing machine:

Order Estimated Machine time(hr) Due Date (hr from now)
1 10 12
2 3 8
3 15 18
4 9 20
5 7 21

The due dates reflect the need for the order to be at its next operation.
a) develop separate schedules by using the FCFS,SPT and EDD rules. Compare the schedules on the basis of average flow time,the average early time and average past due hours for any order.
b)For each schedule,calculate the average WIP inventory(in orders) and the average total inventory( in orders)
c) comment on the performance of the two rules relative to these measures

Purchase this Solution

Solution Summary

Solution contains schedules of overtime by using the FCFS,SPT and EDD rules and compares the schedules on the basis of average flow time,the average early time and average past due hours for any order.Calculations of the average WIP inventory(in orders) and the average total inventory( in orders) for each schedule are also given .

Purchase this Solution


Free BrainMass Quizzes
Solving quadratic inequalities

This quiz test you on how well you are familiar with solving quadratic inequalities.

Geometry - Real Life Application Problems

Understanding of how geometry applies to in real-world contexts

Multiplying Complex Numbers

This is a short quiz to check your understanding of multiplication of complex numbers in rectangular form.

Graphs and Functions

This quiz helps you easily identify a function and test your understanding of ranges, domains , function inverses and transformations.

Exponential Expressions

In this quiz, you will have a chance to practice basic terminology of exponential expressions and how to evaluate them.