Personnel Shortfall
Not what you're looking for?
Using the chart given in the attachment(Personnel_Shortfall.docx), with durations shown in weeks, if there are 16 total people available for the project (assume all 16 are qualified to work on any of the tasks and assume all tasks start and finish at their earliest times), what is the personnel shortfall during weeks 5 and 6?
Purchase this Solution
Solution Summary
The key to answer this question is - "assume all tasks start and finish at their earliest times". Solution explains in layman terms as to how the required personnel shortfall is computed.
Solution Preview
The key to answer this question is - "assume all tasks start and finish at their earliest times."
Look at the chart and figure out which tasks will be going on during weeks 5 and 6 as per the assumption given in the question.
Tasks C(4-7), D(4-8), E(4-6), and ...
Purchase this Solution
Free BrainMass Quizzes
Basic UNIX commands
Use this quiz to check your knowledge of a few common UNIX commands. The quiz covers some of the most essential UNIX commands and their basic usage. If you can pass this quiz then you are clearly on your way to becoming an effective UNIX command line user.
Basic Networking Questions
This quiz consists of some basic networking questions.
Javscript Basics
Quiz on basics of javascript programming language.
Inserting and deleting in a linked list
This quiz tests your understanding of how to insert and delete elements in a linked list. Understanding of the use of linked lists, and the related performance aspects, is an important fundamental skill of computer science data structures.
Excel Introductory Quiz
This quiz tests your knowledge of basics of MS-Excel.