    Personnel Shortfall

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Using the chart given in the attachment(Personnel_Shortfall.docx), with durations shown in weeks, if there are 16 total people available for the project (assume all 16 are qualified to work on any of the tasks and assume all tasks start and finish at their earliest times), what is the personnel shortfall during weeks 5 and 6?

    © BrainMass Inc. brainmass.com October 10, 2019, 5:50 am ad1c9bdddf
    https://brainmass.com/computer-science/c/519670

    Attachments

    Solution Preview

    The key to answer this question is - "assume all tasks start and finish at their earliest times."

    Look at the chart and figure out which tasks will be going on during weeks 5 and 6 as per the assumption given in the question.

    Tasks C(4-7), D(4-8), E(4-6), and ...

    Solution Summary

    The key to answer this question is - "assume all tasks start and finish at their earliest times". Solution explains in layman terms as to how the required personnel shortfall is computed.