Share
Explore BrainMass

Project management, Crashing problem

I have been given a Decision Tree where A is 4 days B is 5 days, C is 2 days, D is 2 days, E is 3 days, F is two days and G is 7 days. I have been told that the benefits are $100.00 per day to crash the project.

I have also been given a chart which says that:

A has a crash duration of 2 days and a slope of 110
B has a crash duration of 2 days and a slope of 40
C has a crash duration of 1 day and a slope of 10
D has a crash duration of 1 day and a slope of 50
E has a crash duration of 3 days and no slope?
F has a crash duration of 1 day and a slope of 40
G has a crash duration of 6 days and a slope of 20

The instructions are to crash the project as far as practical. Can someone show me how this type of problem is done?

Attachments

Solution This solution is FREE courtesy of BrainMass!

Please see the attached file.

Attachments