Project management, Crashing problem
Not what you're looking for?
I have been given a Decision Tree where A is 4 days B is 5 days, C is 2 days, D is 2 days, E is 3 days, F is two days and G is 7 days. I have been told that the benefits are $100.00 per day to crash the project.
I have also been given a chart which says that:
A has a crash duration of 2 days and a slope of 110
B has a crash duration of 2 days and a slope of 40
C has a crash duration of 1 day and a slope of 10
D has a crash duration of 1 day and a slope of 50
E has a crash duration of 3 days and no slope?
F has a crash duration of 1 day and a slope of 40
G has a crash duration of 6 days and a slope of 20
The instructions are to crash the project as far as practical. Can someone show me how this type of problem is done?
Purchase this Solution
Solution Summary
This posting contains a problem on Project crashing. It shows the steps to be followed to solve such a problem.
Purchase this Solution
Free BrainMass Quizzes
Learning Lean
This quiz will help you understand the basic concepts of Lean.
Academic Reading and Writing: Critical Thinking
Importance of Critical Thinking
IPOs
This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)
Paradigms and Frameworks of Management Research
This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.
Operations Management
This quiz tests a student's knowledge about Operations Management