The Crush-a-Matic is the name of the car being designed by Bobby and his friends for the local destruction derby next spring. They plan on working on this project after work and on weekends between now and the event. Bobby's friend Joe is the project planner and has come up with the following activities, times and sequences required to meet the deadline for the derby.

Activity Description Immediate Predecessor Normal Time (days) A Start -- 0 B Purchase Used Car A 14 C Design B 5 D Remove car interior completely B 2 E Rebuild transmission & drive train C, D 30 F Repair and tune engine E 15 G Install roll cage & driver's seat D 7 H Weld doors F, G 2 I Paint H 3 J Final test I 2

A. Determine the critical path for this project. (Do not submit your network diagram, just turn in the path letters. Example - W-T-V-Q)

B. Bobby's car painting connection is finding that his shop is a little slower than expected and would be willing to cut the guys a deal if they can get the car ready for paint earlier. Joe reviewed the project plan and found that three tasks may be shortened by two days; these activities are E, B, and G. Which activities would you choose to shorten, and why?

C. Recalculate the project completion time given the suggestions in part b, what is the new project completion time in days?

Purchase this Solution

Solution Summary

The problem set deals with issues under operations management: Crashing a project and estimating project duration.

Solution provided by:
Education
  • B. Sc., University of Nigeria
  • M. Sc., London South Bank University
Recent Feedback
  • "Thank you."
  • "thank you Chidi Ngene.. if you have any APA references would be great"
  • "Thank you so much for your help, your explanations were easy to understand and apply!"
  • "are you able to highlight the equations used either on the xlsx or a word doc as to how each graph was formed- overall looks fine i just need help understanding this myself"
  • "Chidi Ngene, M. Sc. Was extremely helpful as without the help and guidance I would have failed, but with the help I passed. I still have a lot to learn and in need of the guidance to understand and learn more on the subject. I would recommend Chidi Ngene and BrainMass to anyone that are in need of help. Thank you!!"
Purchase this Solution


Free BrainMass Quizzes
Employee Orientation

Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.

Transformational Leadership

This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.

Team Development Strategies

This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.

Production and cost theory

Understanding production and cost phenomena will permit firms to make wise decisions concerning output volume.