    Oregon: Communications, Materials and inventory, Order entry, Supervision at the plants, General production flow

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    What you expect to find when you arrived in Oregon. Here is some more information you have obtained from management:

    Facilities P and T both claim that parts from the S facility sometimes do not arrive on time, causing costly production shut-downs which periodically lead to missed contractual ship dates.
    The S facility has records that those same parts were loaded onto trailers and that the semi-trailers left on time.
    Facility S habitually runs out of the "accessory" parts which are shipped from the T and P facilities.
    There have been recent instances where over seven shifts of production from a single molding machine have been defective due to a malfunctioning mold.
    Similar quality problems have occurred when the wrong plastic resins have been used for some molded parts.
    Work-in-process (WIP) within the stamping department is sometimes misplaced or lost, disrupting downstream manufacturing processes and leading to missed shipments to the T and P facilities.
    Upon arriving on site and interviewing the production and inventory planning staffs at all three facilities, you hear the following:

    Facility S claims that there have been instances where they have been over one day ahead of their shipping schedule for specific parts, and that the T and P facilities were still claiming they were out of that part. Then, the "missing" parts were located in a still loaded semi-trailer in the yard adjacent to the P and T facilities.
    The production and inventory planning staff at the T and P facilities claim to be shipping the "accessory" parts to the S facility on a JIT (Just in Time) basis and that their shipments should be adequate to support the S facility's requirements on a level production plan.
    The small quality control group at the S facility point out that they do not have the equipment or training to perform quality checks to the same level that facilities P and T are able to perform.
    Due to recent economic conditions, only a single supervisor is available in the stamping department and in the molding department during midnight shifts and on weekends.
    Individual Portion:

    Summarize findings and recommendations on the topics of:

    Communications
    Materials and inventory
    Order entry
    Supervision at the plants
    General production flow

    Summarize your findings and recommendations into a report, including a final summary at the end.

    Group Portion:

    Post your report to the Small Group Discussion Board. Review each members' report. Come to a group consensus on the findings and recommendations.

    Summarize your individual findings and recommendations into a group report. This is your final summary discussing all of the elements from the individual portions. It should be a summary tying everything together with a group consensus.