2. Bridge city developers has the following activity list. draw a project network that can be used to assist in the scheduling of the project activities:

activity a b c d e f g h i j
________________________________________________________
immediate predecessor - - - a,b a,b d e c c f,g,h,i

draw a project network that can be used to assist in the scheduling of the project activities.

3. Construct a project network for the following project. the project is completed when activities f and g are both complete.

activity A B C D E F G
____________________|_____________________________
|
immediate predecessor - - A A c,b c,b d,e

4. Assume that the project in problem 3 has the following activity times (in months).

Activity A B C D E F G
_________________________________

time 4 6 2 6 3 3 5

a. Find the critical path

b. The project must be completed in 1 1/2 years. do you anticipate difficulty in meeting the deadline? Explain.