2. Bridge city developers has the following activity list. draw a project network that can be used to assist in the scheduling of the project activities:
activity a b c d e f g h i j
________________________________________________________
immediate predecessor - - - a,b a,b d e c c f,g,h,i
draw a project network that can be used to assist in the scheduling of the project activities.
3. Construct a project network for the following project. the project is completed when activities f and g are both complete.
activity A B C D E F G
____________________|_____________________________
|
immediate predecessor - - A A c,b c,b d,e
4. Assume that the project in problem 3 has the following activity times (in months).
Activity A B C D E F G
_________________________________
time 4 6 2 6 3 3 5
a. Find the critical path
b. The project must be completed in 1 1/2 years. do you anticipate difficulty in meeting the deadline? Explain.
Purchase this Solution
Purchase this Solution
Free BrainMass Quizzes
Basics of corporate finance
These questions will test you on your knowledge of finance.
Organizational Leadership Quiz
This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.
Accounting: Statement of Cash flows
This quiz tests your knowledge of the components of the statements of cash flows and the methods used to determine cash flows.
Learning Lean
This quiz will help you understand the basic concepts of Lean.
Change and Resistance within Organizations
This quiz intended to help students understand change and resistance in organizations