Project Management: Budget vs. Actual costs
Not what you're looking for?
An inexperienced project manager analyzed the budget vs. actual costs and found that project spending was 10% under budget and was overjoyed at such "good news." What might a seasoned project manager who understands earned value recognize as "not-good-news" about the situation and its impact on the project?
Purchase this Solution
Solution Summary
This solution discusses the scenario from the experienced project manager's point of view.
Solution Preview
The problem is that as the question indicates, spending less isn't always positive, particularly when we analyze the spending in terms of earned value management. We have to look at the amount spent in comparison to the time we have invested into the project and then analyze our spending. If we've spent 60% of our budgeted ...
Purchase this Solution
Free BrainMass Quizzes
Motivation
This tests some key elements of major motivation theories.
Lean your Process
This quiz will help you understand the basic concepts of Lean.
Basic Social Media Concepts
The quiz will test your knowledge on basic social media concepts.
Six Sigma for Process Improvement
A high level understanding of Six Sigma and what it is all about. This just gives you a glimpse of Six Sigma which entails more in-depth knowledge of processes and techniques.
Business Processes
This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.